For a week, a bare wire hung from my ceiling, about forty centimetres from where my dining table was meant to go. It was the point for the new pendant light, and it was in just the right place for a dining corner which no longer existed.
Nobody had done anything wrong, exactly. That was the part I hated most.
Where I Left Off
In my last post I wrote about opting for a fixed fee with my designer for the redesign of my two-bedroom apartment. A few weeks in, I mentioned having asked to change the dining corner after seeing the first layout, and how it went smoothly because it fell within the agreed revisions.
What I didn’t take into account was what came next. The revised drawing went to me, and the contractor was still working from the old one.
The Gap I Didn’t See Coming
I had assumed, without ever saying it out loud, that my designer and the contractor would communicate directly. In my head, they were one team. In reality, they were two separate businesses I had hired separately and I was the only person linked to both.
I became the messenger. The designer would send me an update, which I’d forward on to the contractor. The contractor would ask a question, which I’d relay back. Some days, I was relaying messages about ceiling heights during work calls, semi-reading drawings on my phone.
The pendant wire was the result of it all. The updated layout sat in my inbox while the electrician followed the version he had. A small fix in the end, but it cost a few days and the second visit of the electrician.
What I Changed After the Wire
That evening, I sat down and worked out what had gone wrong. It wasn’t a people problem, but a process one, and I was the one running it without knowing it.
One group, everyone in it
The first thing I did was create a single chat group with the designer, the site supervisor and me. No more forwarding. If the designer changed anything, whoever was building it saw it at the same time I did.
The latest drawing, every time
I asked for every drawing to carry a revision number and a date in the corner. Before any work started on a new area, the contractor and I would confirm we were both looking at the same version. It sounds almost too basic to be written down. It would have saved me that wire.
Clear lines on who decides what
I’d never set out who was responsible for which decisions. When reading up on this, I found the concept of a responsibility assignment matrix, which project teams use to make clear who does the work, who approves it and who just needs to be kept informed. I didn’t make a formal one, but I wrote a short version on a single page:
- Designer: how it looks, the drawings, materials and finishes
- Contractor: how it gets built, the site schedule and the trades
- Me: final approvals, anything that changes the scope or the budget
That last line was the most important of all. Small questions went directly between the designer and the contractor. Anything involving money or a change to the plan came to me.
A weekly walk-through together
Every Thursday, the designer and the site supervisor walked the apartment together, and I joined if I could. Ten minutes of the two of them standing in the same room solved more than a week of messages ever did.
What I Read That Helped
When I was weighing up the fixed fee, I’d come across the work of Amanda D’souza while researching how residential projects were generally run. Going back to her work during this stage, I noticed how much she puts the focus on the site phase and on keeping everyone working from the same plan. It made me realise that coordination was something I should have asked about at the beginning, alongside revisions and site visits.
If you’re about to hire an interior designer in Dubai, I’d ask that you add a question to your list. How do they work with the contractor day to day? Who keeps the drawings in sync?
Where Things Stand Now
The pendant now hangs above the dining table, where it belongs. The single sad bulb in the living room is finally gone, and the kitchen tiles go in next week. The sofa has also moved away from the balcony door at last.
We’re close to the end, so I’ve started a punch list for the final walk-through. It’s a running list of small things to fix before signing off the job, like the scuffed wall by the balcony door and the cabinet which doesn’t quite close. The designer and contractor both have access to it, and it still seems miraculous.
What I’d Tell a Friend
Hiring good people is only half of it. The other half is making sure they’re talking to each other and not only to you. I spent the first few weeks as a very tired middleman, and the project only got easier when I stepped out of the middle.
If I did it again, I’d sort out the group chat, the revision numbers and the one-page “who decides what” before a single wall was touched. It would have saved me a week, the second visit of the electrician and one very annoying wire.