A weather report is not an inspection record
“The site received rain overnight” explains why an inspection may be needed. It does not establish which liner panels were affected, how water reached them or whether covering can proceed.
For a geosynthetic clay liner, a useful record connects the exposure to identifiable material and a defined installation area.
Begin with panel locations, roll identifiers and the approximate exposure period. Distinguish direct rainfall from runoff that crossed surrounding construction areas before reaching the liner.
Record observations that another person can locate
Photographs should show both the overall area and individual concerns. Connect each detail photograph to a marked panel layout.
Inspect accessible areas for fabric damage, folds, displaced bentonite and contamination within overlaps. Record where these conditions occur rather than describing the entire installation as damaged.
Where supporting ground may have softened or eroded, obtain an approved investigation method. Repeatedly lifting and dragging wet material can introduce additional handling problems.
Compare conditions with the supplied product requirements
Different GCL constructions and installation details should not be treated as interchangeable.
Use the approved requirements for the supplied product when reviewing overlaps, seam treatment, handling and protection. A dimension remembered from another project is not a substitute for the applicable detail.
Likewise, a surface that looks dry does not demonstrate that panel integrity and joints remain acceptable. Rainfall alone also does not establish that every exposed panel requires replacement.
Make the decision usable by the next crew
The inspection should finish with an identifiable outcome: released for covering, held for further assessment or requiring an approved corrective action.
State the boundary, responsible person and conditions for release. If corrective work is required, connect the repair reference and inspection photographs to the same location.
Before covering begins, confirm that subsequent activity has not disturbed the accepted section. Approval should describe the area that was assessed, rather than imply that all future work is automatically accepted.
For a fuller inspection sequence, including supporting ground, panel overlaps and release documentation, read: